Skip to main content
BBuildCalcs

Concrete Footing Calculator

This concrete footing calculator estimates exact cubic yards, cubic feet, and 60 lb or 80 lb pre-mixed bags for continuous perimeter wall footings and square structural pad footings.

Published: Updated: By Abubaker Chughtai (Software Engineer & Calculator Developer)
ft
Combined perimeter length of all continuous wall trenches.
in
Typically 2× the stem wall thickness (e.g., 16 in wide for an 8 in block wall).
in
Thickness of the concrete footing itself (IRC minimum is 6 in; 8–12 in is standard).
%
Add 10%–15% for earth-dug trenches or 5%–8% for clean 2×8 wood forms.
$/yd³
Average delivered 3,500–4,000 PSI footing mix runs $150–$195/yd³.
$/bag
Standard 80 lb pre-mixed concrete bags cost $5.50–$7.50 each.
Updates live as you type

Material Estimate

US Imperial
Footing Concrete Volume to Order
2.17cubic yards (yd³)
58.67 cu ft total (53.33 cu ft net + 10% waste)
80 lb Pre-Mixed Concrete Bags
98bags (80 lb)
0.60 cu ft per bag (7,840 lbs total dry mix)
60 lb Pre-Mixed Concrete Bags
131bags (60 lb)
0.45 cu ft per bag (or 157 × 50 lb bags)
Estimated Concrete Cost
$358.52 (Ready-Mix)
Or $637.00 for 98 × 80 lb bags

How to Use This Concrete Footing Calculator

  1. 1Choose Continuous Wall Strip Footing for perimeter house additions, retaining walls, or stem walls, or select Square / Rectangular Pad Footings for isolated deck posts, carport columns, and porch piers.
  2. 2For continuous footings, enter the total trench perimeter length in feet and the footing width in inches. A standard 8-inch CMU block or poured stem wall typically sits on a 16-inch-wide footing.
  3. 3For isolated pad footings, enter the total number of pads along with the pad length and width in inches (such as 24 in × 24 in for heavy deck beam posts).
  4. 4Enter ONLY the concrete pour thickness (typically 8 to 12 inches)—not the entire frost trench excavation depth—unless you are trench-pouring full-depth concrete up to grade.
  5. 5Set a 10% to 15% waste factor if pouring directly into earth-dug backhoe trenches, or 5% to 8% if pouring inside straight 2×8 or 2×10 lumber forms.

Formula & Material Math

A spread footing distributes concentrated wall or post loads across undisturbed native soil. To convert mixed feet and inch dimensions into cubic yards, convert every inch measurement to feet (divide by 12) before multiplying, then divide cubic feet by 27.

Continuous Strip Wall Footing Cross-Section DiagramFinished Grade8" WallFootingWidth = 16" (4" Toe Each Side)8"–12" ThickBelow Frost
Continuous Wall Footing: Width W is typically 2× stem wall thickness (16" wide × 8" thick) resting on undisturbed soil below frost depth.
Isolated Square Pad Footing Dimension Diagram6×6 Post or Concrete PierPad Length (24")Pad Width (24")12"24" × 24" × 12" Pad = 4.00 cu ft (7 × 80 lb Bags Net)
Isolated Square Pad Footing: Pad Length × Pad Width × Pour Thickness × Number of Pads.
1. Continuous Wall Strip Footing Volume
Net Volume (cu ft) = Wall Length (ft) × (Footing Width in ÷ 12) × (Footing Depth in ÷ 12)

Multiplies total linear footage of the foundation perimeter by the cross-sectional width and thickness in feet.

2. Square or Rectangular Pad Footing Volume
Net Volume (cu ft) = Number of Pads × (Pad Length in ÷ 12) × (Pad Width in ÷ 12) × (Depth in ÷ 12)

Computes the cubic feet of a single isolated pier pad and multiplies by the total number of column bases.

3. Ready-Mix Cubic Yards & Bagged Concrete Equivalents
Cubic Yards (yd³) = [Net Volume × (1 + Waste % ÷ 100)] ÷ 27
80 lb Bags = CEILING(Total Volume in cu ft ÷ 0.60)
60 lb Bags = CEILING(Total Volume in cu ft ÷ 0.45)

One cubic yard equals 27 cubic feet (45 bags of 80 lb concrete or 60 bags of 60 lb concrete).

Example Calculation: 60 Linear Feet of 16" × 8" Garage Addition Strip Footing

Project Scenario: You are building a 20 ft × 20 ft three-wall garage addition attached to an existing house (60 linear feet of new perimeter wall). Local plans call for a 16-inch-wide by 8-inch-thick continuous footing formed with 2×8 boards and a 10% waste factor.

Step 1: Convert Width and Depth from Inches to Feet
16 in ÷ 12 = 1.333 ft wide | 8 in ÷ 12 = 0.667 ft thick
= 1.333 ft × 0.667 ft cross-section
Step 2: Calculate Net Footing Volume in Cubic Feet
60 ft × 1.3333 ft × 0.6667 ft
= 53.33 cu ft
Step 3: Add 10% Trench & Subgrade Waste Allowance
53.33 cu ft × 1.10
= 58.67 cu ft
Step 4: Convert to Cubic Yards for Ready-Mix Truck
58.67 cu ft ÷ 27 cu ft/yd³
= 2.17 cubic yards
Step 5: Compare 80 lb Pre-Mixed Bag Count
CEILING(58.67 ÷ 0.60)
= 98 bags (80 lb)
Order 2.25 to 2.5 cubic yards of 3,500+ PSI ready-mix concrete (~$358 before short-load delivery fee) rather than mixing 98 eighty-pound bags (7,840 lbs of dry mix) by hand so the entire perimeter cures monolithically without cold joints.

Standard Spread Footing Dimensions & Concrete Yield Chart

Net concrete volume and 80 lb bag counts for common residential strip footings (per 10 linear feet) and isolated pier pads (per pad) before waste.

Footing Size (W × Thick)Common Structural UseNet Cubic FeetNet Cubic Yards80 lb Bags (Net)
12" × 6" (per 10 LF)Light garden walls, small shed curbs5.00 cu ft0.19 yd³9 bags
16" × 8" (per 10 LF)Standard 8" CMU block or 1-story wall8.89 cu ft0.33 yd³15 bags
20" × 10" (per 10 LF)2-story house addition or brick veneer13.89 cu ft0.51 yd³24 bags
24" × 12" (per 10 LF)Heavy load-bearing or soft clay soil20.00 cu ft0.74 yd³34 bags
18" × 18" × 8" Pad (1 pad)Porch post or pergola column base1.50 cu ft0.06 yd³3 bags
24" × 24" × 12" Pad (1 pad)Main deck girder beam or carport post4.00 cu ft0.15 yd³7 bags

How Much Concrete for a Footing? Sizing Continuous Wall vs. Pad Footings

When using a wall footing concrete calculator or pad footing calculator, distinguish between excavation depth and concrete pour thickness. Even if your local frost line sits 36 or 42 inches below grade, builders rarely fill the entire 42-inch trench with solid footing concrete. Instead, you excavate down below frost depth to undisturbed soil, pour an 8-inch to 12-inch thick spread footing at the bottom of the trench, and build an 8-inch CMU block wall, poured stem wall, or cylindrical pier from the top of the footing up above grade.

Under traditional residential rules of thumb aligned with International Residential Code (ICC IRC Chapter 4) prescriptive tables for standard 2,000 psf bearing soil, spread footing dimensions usually measure twice the width of the supported wall and match the wall thickness in vertical depth. For example, an 8-inch concrete block foundation wall commonly rests on a 16-inch-wide by 8-inch-deep footing with at least 4 inches of toe projection on each side. Always check your local building department soil tables, as soft clay or multi-story snow loads often require 20-inch or 24-inch footings.

Ordering Bags of Concrete for Footings vs. Ready-Mix Delivery

Pre-mixed bags of concrete for footings work great when pouring four to six isolated 24×24 deck pier pads (which take 7 bags of 80 lb QUIKRETE Concrete Mix per pad, or 28 bags total). Because each pad is a separate structural element, mixing three or four batches in a wheelbarrow per hole poses zero risk of creating a weak seam.

Continuous perimeter wall footings are different: structural footings act as a continuous reinforced beam bridging soft spots in the soil. Once a strip footing exceeds 35 to 45 eighty-pound bags (about 0.8 to 1.0 cubic yards), ordering a single ready-mix truck per NRMCA placement guidelines ensures uniform slump and prevents cold joints around corners.

Practical Pro Tips & Common DIY Mistakes to Avoid

Practical Pro Tips

  • • Pour footings directly onto firm, undisturbed native soil. If your excavator digs 3 inches too deep in one spot, fill that low spot with concrete or compacted crushed stone—never loose dug dirt backfilled into the trench.
  • • Support two continuous #4 (1/2-inch) horizontal rebar rods on 3-inch concrete dobies or plastic rebar chairs—never lay rebar flat in the dirt and try to "pull it up" during the pour.
  • • Form a 1.5" × 1.5" bevelled keyway groove (using a oiled 2×2 strip) or install vertical #4 L-dowels every 32 to 48 inches before the footing sets to lock your stem wall against lateral soil pressure.
  • • Drive grade stakes every 6 to 8 feet with a laser level or string line so you screed the top of the footing dead level—a level footing makes laying the first course of CMU block dramatically faster.

Common Mistakes to Avoid

  • • Entering the 36-inch or 48-inch frost line hole depth into the Concrete Pour Thickness field when only pouring an 8-inch thick footing pad at the bottom of the excavation.
  • • Ordering zero waste for earth-formed trenches—a 16-inch backhoe bucket routinely tears side walls out to 18 inches, consuming 12% to 15% extra concrete.
  • • Pouring footing concrete onto frozen ground or standing rainwater at the bottom of the trench, which destroys compressive strength and causes settlement cracks.
  • • Overlap-splicing continuous #4 rebar by only 4 or 6 inches at corners instead of providing a full 20-inch to 24-inch lap splice and bent corner bars (L-bars).

Frequently Asked Questions

How wide and thick should a concrete footing be for an 8-inch block wall?
A common residential rule of thumb for firm undisturbed soil (2,000+ psf load-bearing capacity) makes the continuous footing twice as wide as the foundation wall and at least as thick as the wall width. For an 8-inch CMU block wall, that equals a 16-inch-wide by 8-inch-thick footing, leaving a 4-inch projection on both sides of the block. Always verify against IRC Table R403.1 and your local building permit office.
How many 80 lb bags of concrete do I need for a 20-foot continuous footing?
A 20-foot-long continuous wall footing measuring 16 inches wide by 8 inches thick holds 17.78 cubic feet (0.66 cubic yards) of concrete net. Divided by 0.60 cubic feet per 80 lb bag, that takes 30 bags net—or 33 bags of 80 lb concrete once you include a 10% earth-trench waste factor.
Can I pour concrete footings directly into a dirt trench without wood forms?
Yes, in stiff cohesive clay or loam soils that hold clean vertical trench walls without caving in, contractors frequently trench-pour footings without lumber forms, using driven rebar stakes and nails to mark the level screed height. In sandy, gravelly, or sloughing soil, build 2×8 or 2×10 wood forms so cave-ins do not contaminate the wet concrete.
What PSI concrete is best for residential house and deck footings?
Most US residential building codes require a minimum compressive strength of 2,500 to 3,000 PSI for footings in mild climates and 3,500 to 4,000 PSI in moderate-to-severe weathering (freeze-thaw) regions. Standard bagged concrete mix and residential ready-mix flatwork/footing blends typically cure to 3,500–4,000 PSI at 28 days.
Do concrete pad footings for deck posts need rebar?
While small unreinforced concrete pads under light freestanding low decks sometimes pass prescriptive code if thick enough to resist punching shear, adding a simple tic-tac-toe grid of three #4 rebar bars each way (spaced 3 inches clear of the bottom earth) in a 24" × 24" × 12" pad costs under $15 and prevents the pad from cracking under heavy concentrated post loads.
How long must a concrete footing cure before laying block or framing walls?
Under normal temperatures (55°F–80°F), masons can usually snap chalk lines and start laying the first course of CMU block or setting wall forms 24 to 48 hours after pouring the footing. However, wait at least 7 days (roughly 70% design strength) before applying heavy structural framing loads or backfilling against foundation walls.

Standards, Spec Sheets & Further Reading

Embed This Concrete Footing Calculator on Your Website

Contractors, hardware stores, and DIY bloggers can embed this live calculator for free with attribution back to BuildCalcs.